Expedite/Coordinate Critical Industrial Track Open Cut Operation
On September 5, 2022, our client at Agua Mansa Commerce Park faced a need to make changes in their construction timeline with their vast Storm Drain infrastructure project operated by Riverside County Flood Control. On September 6, On Track Solutions was tasked to initiate/expedite the planning of an Open Cut Track Removal for a Storm Drain man-hole 3-junction installation under an Industry Track within this project area . On September 15, On Track Solutions coordinated with Union Pacific Railroad, KPRS Construction Services, Boudreau Pipeline and RAILWORKS to have the track removed, storm drain installed, man-hole constructed, and track put back place for service within 96 hours.
industry track Open Cut removal
Once Union Pacific Railroad Train Operations made their last delivery before the weekend, On Track Safety was put in place by UPRR Safety Flagger,. With careful coordination/collaboration RAILWORKS and Boudreau Pipeline Corporation began the task of safely removing the track providing the work area for the Storm Drain work to be performed. Boudreau Pipe Corporation began the Storm Drain installation that included approximately 150 ft of 84” RCP (reinforced concrete pipe), 160 ft of 48” RCP and building man-hole to connect to an existing 66” RCP pipe. By Saturday evening, September 17, (Day 3), the all work for Storm Drain installation was complete with construction of manhole and ready for track installation. On Sunday morning, September 18, Rail Works and Boudreau Pipeline Corporation executed the installation flawlessly. Railworks installed the track within UPRR requirements and track was ready for service, (TOTO) All work was successfully performed within a 72 hour work window.